Where is Steynton Road And Sheffield Drive - Micro Energy Battery Storage up to?

Each status below comes from a named source and date.

Battery · Wales

Planning

Planning
Granted
6 May 2026
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_27d55af518c6557c

Measures

Rated power
0.2 MW
Connection capacity
Not published
Storage energy
Not published