Solar PV · England, South West
Planning
- Planning
- Granted
- 19 Mar 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 20 Jan 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 31 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_296bde33569d5067
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published