Projects
Where is Trevol Business Park up to?
Each status below comes from a named source and date.
Battery · England, South West
Planning
- Planning
- Granted
- 2 Sep 2019
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_2a3d97c53327b6c8
Measures
- Rated power
- 10.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published