Where is Craigannet Farm Wind Turbine up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
16 Aug 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Dec 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
31 Mar 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_2bbfd8e86e948c3c

Measures

Rated power
1.5 MW
Connection capacity
Not published
Storage energy
Not published