Projects
Where is Dominos Pizza, Skyline Drive - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, North West
Planning
- Planning
- Granted
- 14 Feb 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_2f31c90656d91b4a
Measures
- Rated power
- 1.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published