Solar PV · England, South East

Planning

Planning
Granted
17 May 2011
DESNZ REPD, 3 Aug 2026
Construction
Built
3 Dec 2012
DESNZ REPD, 3 Aug 2026
Operational status
Operational
21 Feb 2013
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_2fdf5ae6244dea92

Measures

Rated power
5.4 MW
Connection capacity
Not published