Where is Awel y Mor Offshore Wind Farm up to?
Each status below comes from a named source and date.
Offshore wind · Wales, Offshore
Planning
- Planning
- Granted
- 20 Sep 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Offshore wind project, epj_300c499aedc0d1ed
Measures
- Rated power
- 775.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published