Projects
Where is Diageo Biomass Energy Project up to?
Each status below comes from a named source and date.
Biomass · Scotland
Planning
- Planning
- Granted
- 4 Nov 2008
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Aug 2009
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 8 May 2013
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Biomass project, epj_308e2dee515789ce
Measures
- Rated power
- 5.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published