Where is Principality Stadium, Westgate Street - Solar panels up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- 30 Sep 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 12 Jun 2026
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_3112d6c25ced4610
Measures
- Rated power
- 1.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published