Projects
Where is Highbury Poultry Produce, Manor House Lane - Solar Array up to?
Each status below comes from a named source and date.
Solar PV · England, West Midlands
Planning
- Planning
- Granted
- 13 Jan 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_3278e81ac4671316
Measures
- Rated power
- 0.6 MW
- Connection capacity
- Not published
- Storage energy
- Not published