Projects
Where is West Berkshire Community Hospital, Rookes Way - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, South East
Planning
- Planning
- Granted
- 9 Apr 2024
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_3329431be5d3432c
Measures
- Rated power
- 0.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published