Projects
Where is Scunthorpe General Hospital, Cliff Gardens - Solar Panels up to?
Each status below comes from a named source and date.
Solar PV · England, Yorkshire and Humber
Planning
- Planning
- Application submitted
- 3 Dec 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_33e809166705a87f
Measures
- Rated power
- 0.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published