Projects
Where is Buttercombe Lane - Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, South West
Planning
- Planning
- Granted
- 26 Mar 2026
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_341997c7cccf1dba
Measures
- Rated power
- 15.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published