Onshore wind · England, North West

Planning

Planning
Granted
16 Oct 2012
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Jan 2014
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Feb 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_345e5070f5afb19f

Measures

Rated power
1.5 MW
Connection capacity
Not published