Where is Ford Motor Company Ltd (Extension) up to?

Each status below comes from a named source and date.

Onshore wind · England, London

Planning

Planning
Granted
16 Jul 2009
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Jan 2010
DESNZ REPD, 3 Aug 2026
Operational status
Operational
12 Aug 2011
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_360208eeb6f65437

Measures

Rated power
2.0 MW
Connection capacity
Not published
Storage energy
Not published