Where is Crow Trees Farm up to?

Each status below comes from a named source and date.

Solar PV · England, East Midlands

Planning

Planning
Granted
25 Jun 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Nov 2015
DESNZ REPD, 3 Aug 2026
Operational status
Operational
23 Mar 2016
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_36749a74d4ae6386

Measures

Rated power
4.7 MW
Connection capacity
Not published