Grid

Projects

Projects

Where is Trident Park up to?

Each status below comes from a named source and date.

Energy from waste · Wales

Planning

Planning
Granted
29 Jun 2010
DESNZ REPD, 3 Aug 2026
Construction
Built
30 Jul 2012
DESNZ REPD, 3 Aug 2026
Operational status
Operational
10 Mar 2015
DESNZ REPD, 3 Aug 2026

Connection

Connection
Energy from waste project, epj_38b4c539f94e837a

Measures

Rated power
30.0 MW
Connection capacity
Not published
Storage energy
Not published