Grid

Projects

Projects

Where is Hawkesyard Estate, Rugeley Road - Battery Energy Storage up to?

Each status below comes from a named source and date.

Battery · England, West Midlands

Planning

Planning
Application submitted
16 Oct 2025
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Battery project, epj_39bae2649dd9268b

Measures

Rated power
100.0 MW
Connection capacity
Not published
Storage energy
Not published