Where is Tees Renewable Energy Plant up to?

Each status below comes from a named source and date.

Biomass · England, North East

Planning

Planning
Permission expired
DESNZ REPD, 3 Aug 2026
Construction
Built
NESO TEC register, 13 Oct 2026
Operational status
Operational
NESO TEC register, 13 Oct 2026

Connection

Connection
Connected
NESO TEC register, 13 Oct 2026

Measures

Rated power
299.0 MW
Connection capacity
285.0 MW
Storage energy
Not published