Where is Lister Drive up to?
Each status below comes from a named source and date.
Battery · England, North West
Planning
- Planning
- Granted
- 2 Mar 2021
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 May 2021
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Connected
- NESO TEC register, 13 Oct 2026
Measures
- Rated power
- 49.9 MW
- Connection capacity
- 20.0 MW
- Storage energy
- Not published