Where is Hill of Lybster up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
22 Jun 2001
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
8 Feb 2003
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_3e26863e8e693a4a

Measures

Rated power
4.9 MW
Connection capacity
Not published
Storage energy
Not published