Projects
Where is Neilston Greener Grid Park up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 28 Apr 2022
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 29 Aug 2023
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_400f2349d487c3c7
Measures
- Rated power
- 50.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published