Projects
Where is Hams Hall - Battery Energy Storage System up to?
Each status below comes from a named source and date.
Battery · England, West Midlands
Planning
- Planning
- Granted
- 4 Mar 2022
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Jan 2025
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_42b38ddaf9d467b5
Measures
- Rated power
- 400.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published