Projects
Where is Carland Cross Wind Farm Repowering up to?
Each status below comes from a named source and date.
Onshore wind · England, South West
Planning
- Planning
- Granted
- 20 Jan 2010
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 23 Jan 2013
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 30 Oct 2013
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_449a96c7dcf68f55
Measures
- Rated power
- 20.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published