Where is Boyndie Airfield up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
23 Jul 2004
DESNZ REPD, 3 Aug 2026
Construction
Built
1 Sep 2005
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 Feb 2006
DESNZ REPD, 3 Aug 2026

Connection

Connection
Onshore wind project, epj_451ebcde4fe6e194

Measures

Rated power
16.7 MW
Connection capacity
Not published