Where is Bhlaraidh (previously Balmacaan) up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- 17 Jan 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Mar 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 15 Sep 2017
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_47ca92c76ff6bc17
Measures
- Rated power
- 110.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published