Where is Bad a Cheo Wind Farm up to?

Each status below comes from a named source and date.

Onshore wind · Scotland

Planning

Planning
Granted
6 May 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
15 Mar 2017
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 May 2019
DESNZ REPD, 3 Aug 2026

Connection

Connection
Connected
NESO TEC register, 13 Oct 2026

Measures

Rated power
26.7 MW
Connection capacity
26.6 MW
Storage energy
Not published