Where is Bad a Cheo Wind Farm up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- 6 May 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 15 Mar 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 May 2019
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Connected
- NESO TEC register, 13 Oct 2026
Measures
- Rated power
- 26.7 MW
- Connection capacity
- 26.6 MW
- Storage energy
- Not published