Projects
Where is Wrexham Social Housing PV up to?
Each status below comes from a named source and date.
Solar PV · Wales
Planning
- Planning
- Granted
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Mar 2012
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Aug 2012
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_4a8a3372e9c33a3b
Measures
- Rated power
- 5.4 MW
- Connection capacity
- Not published
- Storage energy
- Not published