Where is Willsland Solar farm up to?

Each status below comes from a named source and date.

Solar PV · England, South West

Planning

Planning
Granted
7 Mar 2012
DESNZ REPD, 3 Aug 2026
Construction
Built
10 Jan 2013
DESNZ REPD, 3 Aug 2026
Operational status
Operational
21 Mar 2013
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_4b50a4e0981a38a0

Measures

Rated power
3.2 MW
Connection capacity
Not published
Storage energy
Not published