Where is Whites Landfill Site (Canford) up to?

Each status below comes from a named source and date.

Landfill gas · England, South West

Planning

Planning
Granted
13 May 1993
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
1 May 1996
DESNZ REPD, 3 Aug 2026

Connection

Connection
Landfill gas project, epj_4d1721182d7a194b

Measures

Rated power
6.0 MW
Connection capacity
Not published
Storage energy
Not published