Projects
Where is ABB & UK Power Networks Energy Storage Installation up to?
Each status below comes from a named source and date.
Battery · England, Eastern
Planning
- Planning
- Granted
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Nov 2010
- DESNZ REPD, 3 Aug 2026
- Operational status
- Closed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_4d54dd983e0de2ae
Measures
- Rated power
- 0.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published