Projects
Where is South Leylodge Farmhouse, Kintore - Battery Energy Storage System up to?
Each status below comes from a named source and date.
Battery · Scotland
Planning
- Planning
- Granted
- 20 Apr 2023
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_4f4ed291df4d6c27
Measures
- Rated power
- 49.9 MW
- Connection capacity
- Not published
- Storage energy
- Not published