Onshore wind · Scotland
Planning
- Planning
- Granted
- 6 Jul 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 19 Jul 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 23 Jan 2018
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_4f5fc197a6b6cab8
Measures
- Rated power
- 9.2 MW
- Connection capacity
- Not published
- Storage energy
- Not published