Where is Wether Hill up to?
Each status below comes from a named source and date.
Onshore wind · Scotland
Planning
- Planning
- Granted
- 1 Mar 2005
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Aug 2006
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 May 2007
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Gate 1, Agreement held
- 29 Sep 2031
- NESO TEC register, 13 Oct 2026
Measures
- Rated power
- 18.2 MW
- Connection capacity
- 66.0 MW
- Storage energy
- Not published