Where is The Stables up to?

Each status below comes from a named source and date.

Solar PV · England, East Midlands

Planning

Planning
Granted
14 Apr 2014
DESNZ REPD, 3 Aug 2026
Construction
Built
DESNZ REPD, 3 Aug 2026
Operational status
Operational
22 Aug 2014
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_51a5de111f2ccd55

Measures

Rated power
1.8 MW
Connection capacity
Not published
Storage energy
Not published