Onshore wind · Scotland

Planning

Planning
Granted
15 Dec 2021
DESNZ REPD, 3 Aug 2026
Construction
Under construction
1 Sep 2025
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Gate 2, Agreement held
30 Nov 2026
NESO TEC register, 13 Oct 2026

Measures

Rated power
46.2 MW
Connection capacity
43.6 MW
Storage energy
Not published