Grid

Projects

Projects

Where is Land at Hill Farm up to?

Each status below comes from a named source and date.

Solar PV · England, Eastern

Planning

Planning
Withdrawn
23 May 2013
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_5524fb897101b5cc

Measures

Rated power
10.0 MW
Connection capacity
Not published
Storage energy
Not published