Where is Langenhoe Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, Eastern
Planning
- Planning
- Granted
- 29 Aug 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 8 Sep 2014
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 4 Mar 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_5614c91cbdd7e48f
Measures
- Rated power
- 21.3 MW
- Connection capacity
- Not published
- Storage energy
- Not published