Onshore wind · Wales
Planning
- Planning
- Granted
- 8 Feb 2013
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 8 Feb 2017
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 24 Apr 2019
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_573bc8f89880e4e0
Measures
- Rated power
- 32.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published