Projects
Where is The Glowhouse up to?
Each status below comes from a named source and date.
Battery · England, North West
Planning
- Planning
- Granted
- 21 Oct 2020
- DESNZ REPD, 3 Aug 2026
- Construction
- Under construction
- 1 Jan 2022
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Battery project, epj_57ad139eed813e94
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published