Solar PV · England, East Midlands
Planning
- Planning
- Granted
- 10 Nov 2015
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 29 Feb 2016
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 30 Mar 2016
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_57cec046840504b8
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published