Where is Land West Of Hunger Hill Farm up to?

Each status below comes from a named source and date.

Solar PV · England, North East

Planning

Planning
Granted
13 Aug 2015
DESNZ REPD, 3 Aug 2026
Construction
Built
12 Dec 2016
DESNZ REPD, 3 Aug 2026
Operational status
Operational
15 Feb 2017
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_599a83e0da15265b

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published