Grid

Projects

Projects

Where is Home Farm, Hursley Park Road - Solar Panels up to?

Each status below comes from a named source and date.

Solar PV · England, South East

Planning

Planning
Granted
26 Jun 2025
DESNZ REPD, 3 Aug 2026
Construction
Not started
DESNZ REPD, 3 Aug 2026
Operational status
Proposed
DESNZ REPD, 3 Aug 2026

Connection

Connection
Solar PV project, epj_5a0b25f1bc9ff769

Measures

Rated power
5.0 MW
Connection capacity
Not published
Storage energy
Not published