Solar PV · England, South East
Planning
- Planning
- Granted
- 5 Sep 2014
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Jan 2015
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 28 Mar 2015
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_5b849d1a47765baa
Measures
- Rated power
- 8.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published