Solar PV · England, North West
Planning
- Planning
- Permission expired
- 31 May 2019
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_5be9e907d3f55bdf
Measures
- Rated power
- 5.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published