Where is Cambrian Cross Country, Trefilan - Wind Turbine up to?
Each status below comes from a named source and date.
Onshore wind · Wales
Planning
- Planning
- Granted
- 21 Aug 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_5c330731cd16696d
Measures
- Rated power
- 0.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published