Projects
Where is Hardingham Solar Farm up to?
Each status below comes from a named source and date.
Solar PV · England, Eastern
Planning
- Planning
- Granted
- 21 Dec 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 5 Jan 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_5f02b79d224a754f
Measures
- Rated power
- 14.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published