Onshore wind · Scotland
Planning
- Planning
- Granted
- 29 Feb 2012
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 30 Apr 2013
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Apr 2014
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Onshore wind project, epj_5f3458421b3fc9a7
Measures
- Rated power
- 7.5 MW
- Connection capacity
- Not published
- Storage energy
- Not published