Solar PV · England, South West
Planning
- Planning
- Granted
- 15 Apr 2025
- DESNZ REPD, 3 Aug 2026
- Construction
- Not started
- DESNZ REPD, 3 Aug 2026
- Operational status
- Proposed
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_603b43ff7b4af5f8
Measures
- Rated power
- 0.8 MW
- Connection capacity
- Not published
- Storage energy
- Not published