Solar PV · England, Eastern
Planning
- Planning
- Granted
- 23 Dec 2021
- DESNZ REPD, 3 Aug 2026
- Construction
- Built
- 1 Dec 2023
- DESNZ REPD, 3 Aug 2026
- Operational status
- Operational
- 1 Oct 2024
- DESNZ REPD, 3 Aug 2026
Connection
- Connection
- Solar PV project, epj_606e774388d18ace
Measures
- Rated power
- 35.0 MW
- Connection capacity
- Not published
- Storage energy
- Not published